In 1987, San Diego region voters approved the TransNet program - a half cent sales tax to fund a variety of important transportation projects throughout the region.
The $3.3 billion, 20-year TransNet program plays a critical role in San Diego's mobility - building and improving highways in our region, adding Trolley lines and Coaster commuter rail service, and improving local streets. The current TransNet program expires in 2008.
Please join SANDAG at a celebration of the opening of SR 125 from SR 52 to SR 54.
Here are just a few TransNet projects underway in the region.

| Project Description |
Project Stage |
Estimated Completion |
SR 56
4-Lane Freeway
from Black Mountain Road to Camino Ruiz |
Construction |
April 2003 |
SR 125
6-Lane Freeway
from SR 94 to Troy Street |
Construction |
May 2003 |
SR 125
6-Lane Freeway
from I-8 to SR 52 |
Construction |
July 2003 |
Mission Valley East Trolley Extension
through San Diego State University |
Construction |
May 2005 |
List of additional projects funded by TransNet (pdf).
Project manager: José Nuncio
(619) 595-5619
|